NY-Industrial Plant

43.155478
-77.615983
13
Site LocationRochester, NY
Site TypeManufacturing Site
Start Date2004
GeologyGlacial till overburden lying above fractured sedimentary bedrock.
Media TreatedGroundwater in bedrock
Contaminant TreatedMethylene chloride, 1,2-dichloropropane, 1,2-dichlorethane
Initial Contaminant Concentration500,000 ug/L
Final Contaminant Concentration50,000 ug/L
Type of NanoparticlenZVI
Length of OperationN/A